Council have completed the repair and rehabilitation of Rawdon Island Bridge in partnership with Councils contractor Duratec Ltd.
Following the March 2021 floods, we completed underwater inspections of our entire bridge network. Through these underwater inspections, we found major structural issues with the pylons supporting Rawdon Island Bridge. The impairments were significant and to manage public safety, we closed the bridge and the waterway beneath it to all traffic between Monday 5 July 2021 and Monday 30 August 2021.
Significant investigations and design was undertake to inform the works, with underwater repairs being completed in February 2022 allowing load limits and traffic restrictions to be removed.
Above water repairs to the concrete piers, bridge girders and the deck was completed December 2022. This included the installation of a corrosion protection system on the bridge to increase the useful life of the structure, which was commission in August 2023.
Completed works
Physical works on the bridge were completed in December 2022 and the cathodic protection system commissioned in August 2023. The Project is now complete.
The benefits realised by completion of the Rawdon Island Repair Project was the reinstatement of critical infrastructure providing the link to the Rawdon Island community, and included:
Rawdon Island Road, 2446 View Map
Rawdon Island Road , 2446