Fixing Country Bridges Program

Logans Crossing Bridge

The Fixing Country Bridges Program is a NSW Government initiative, enabling councils to replace timber bridges in poor condition and better connect regional and rural communities.

Port Macquarie-Hastings Council has been successful in securing funding of $19.455m under round one of the program, to assist in the replacement of the following 13 high priority bridges across our LGA.

Planned Project Delivery

The program is being delivered in two packages. Project environmental approvals and design phase works for both of these packages was completed in December 2022.

Procurement processes for the engagement of suitable External Major Contractors for the two packages are now completed.

  • Package 1 - Major Bridges: Saunders Civilbuild P/L
  • Package 2 - Minor Bridges and Culverts: EIRE Constructions P/L

Construction phase works commenced in May 2023 with all programs works expected to be completed by mid 2024 (weather permitting) to meet the timeframes outlined in the funding guidelines.

Benefits of the bridge replacements

The replacement of these nominated bridges, with new concrete structures, has a range of community benefits including bringing these older structures up to current Australian Standards and providing greater resistance to flood damage including reduced return to service times following flooding inundation of these bridge crossings.

It will reduce long term maintenance costs to Council, and provide improved safety for pedestrians, vehicles and cyclists. It will also improve traffic flow and access for businesses and residents.

This project forms a significant part of Council's commitment to continue to deliver key road infrastructure, and connecting our communities.

 

King Creek Bridge - King Creek

Location:

King Creek Road, King Creek

Status:

Commencement expected March / April 2024

Timing:

Scheduled for completion TBC

 When Works Commence

Road closed:

Yes

Side track:

No side track available

Detour:

Detour Via Cameron St Wauchope onto Bago Road

FCB-King-Creek-Bridge-Detour-Map-2023-12-06.png

Works will be commencing on King Creek Bridge in early 2024. Once underway, this project may take up to 6 months to complete, weather permitting.

We are currently awaiting final approvals from Essential Energy for the relocation of overhead powerlines. These approvals have progressed and construction commencement is now expected late March/early April 2024.

We will keep you informed via VMS boards near the work site and this website.

Bridge on Bril Bril Road (Bottlebrush No.1) - Rollands Plains

Location:

Bril Bril-Bellangry Road, Rollands Plains

Status:

Delayed

Timing:

Scheduled for completion March 2024

Road closed:

Yes

Side track:

Side-track in place

Detour:

No detour required

 

FCB Bril Bril Rd Bottlebrush 1

 

Langdons Bridge (Bottlebrush No.2) - Rollands Plains

Location:

Bril Bril-Bellangry Road, Rollands Plains

Status:

On schedule

Timing:

Scheduled for completion March 2024

Road closed:

Yes

Side track:

No side track available

Detour:

No detour required

 

Langdons Bridge (Bottlebrush No.2) is deemed to be of low use and therefore the decision has been made to complete these works under a full road closure with no detour provided or available. The community who may use this bridge has been adequately notified.

FCB Langdons Bridge Bottlebrush 2 Bridge

Little Mortons Creek Bridge

Location:

Mortons Creek Road, Mortons Creek

Status:

Complete and open to traffic

 

FCB Little Mortons Creek Bridge Detour

 

Crowe Roods Bridge - Mortons Creek

Location:

Bellangry Road, Mortons Creek

Status:

Complete and open to traffic

 

FCB Crowe Roods Bridge Mortons Creek

Cutty Creek Bridge & Joes Bridge Bobs Creek

Location:

Bobs Creek Road, Bobs Creek/Cutty Creek

Status:

Cutty Creek Bridge - Complete and open to traffic

Joes Bridge - Complete and open to traffic

 

Cutty Creek and Joes Bridge locations

Donkins Flat Bridge - Comboyne

Location:

Wingham Road, Comboyne

Status:

Complete and open to traffic

 

FCB Donkins Flat Bridge Comboyne

Farrawells Road Bridge, Farrawells Road, Telegraph Point

Location:

Farrawells Road, Pembrooke/Telegraph Point

Status:

Complete and open to traffic

 

Logans Crossing Bridge - Logans Crossing

Location:

Logans Crossing Road, Logans Crossing

Status:

Complete and open to traffic

Old School Road Bridge - Herons Creek

Location:

Old School Road, Herons Creek

Status:

Complete and open to traffic

Thone River Road Bridge - Byabarra

Location:

Thone River Road, Byabarra

Status:

Complete and open to traffic

 

Thone River Road Bridge will be delivered under a full road closure with no bypass or detour. Property access will be discussed with the community ahead of works commencing.

FCB Thone River Rd Bridge Byabarra

Tower Road Bridge, Pembrooke Village

Location:

Tower Road, Pembrooke Village

Status:

Complete and open to traffic