Why is the Cowarra Water Supply Scheme needed?
With the population expected to reach 119,027 by 2050, this project is essential for water security, infrastructure resilience, and sustainable development.
How will supply volume meet demand?
The scheme will increase water supply capacity, ensuring we can meet demand until around 2070, even with potential long dry periods due to climate change.
When are the works scheduled?
The final design stage will start in mid 2026, with construction beginning late 2026. The entire construction process, including commissioning, will take about two years to complete.
What will the hours of construction be?
Most construction activities will occur within standard hours:
- Monday to Friday: 7:00 am to 6:00 pm.
- Saturday: 8:00 am to 3:30 pm.
- No work on Sundays or public holidays In exceptional cases, some activities may take place outside these hours, subject to consultation with nearby residents and obtaining a permit.