Village Sewerage Scheme: Comboyne, Long Flat and Telegraph Point

Autumn in Comboyne Village
Comboyne Village

Construction has commenced on the Telegraph Point and Comboyne sewerage schemes with commence at Long Flat in July 2019.

In August 2018, Council awarded Ledonne Constructions the contract to construct the village sewerage schemes in Comboyne, Long Flat and Telegraph Point.

All three communities will benefit from the construction of new sewerage treatment plants and full collection systems which will include a gravity sewer at Long Flat and Comboyne. A pressure sewer system will be installed at Telegraph Point which will also be constructed under the contract.

Sewage waste disposal within the 3 villages is currently through on-site sewerage management systems, and the new fully reticulated sewerage network will provide a more efficient disposal method, and importantly protect the environment and health of the local community.

Providing the systems in the 3 villages is a total investment of more than $29 million, which is being funded by Council and includes a NSW State Government contribution of almost $6 million under the Restart NSW Water Security for Regions program.

All 3 schemes are scheduled to be completed by July 2020 (weather permitting), with connection for customers to progressively occur from early 2020 onwards.  

Council will provide advice to all landowners when the schemes have been completed (including reticulation and treatment works) with advice when connection can commence and how this is to be done.